Guide No. 7 Applications Johannesburg
Rezoning or Consent Use? Which Application Your Plan Needs
How to tell from Johannesburg’s land use scheme and your title deed whether a plan needs a consent use, a rezoning or neither.
By Glensburg Town Planners
Published Reviewed 10 min read

Rezoning vs consent use in one paragraph
Rezoning and consent use both change what a property may be used for, and in Johannesburg the land use scheme’s Table 2 decides between them. Each zone’s row sorts uses into primary land use rights, which need no application, secondary land use rights, for which the City’s consent is needed, and prohibited land uses (cl 10).1 If your use needs consent in your zone, apply for a consent use, and the zoning stays as it is. If it is prohibited, the usual route is a rezoning, which moves the erf into a zone that allows it. Either way, the limits on size and position and the title deed can still stand in the way.
Start from the zone, not from the plan. A consent use asks the City to allow something the scheme already provides for in your zone; a rezoning asks it to change the scheme for your erf. That difference explains the rest: a rezoning is advertised more widely, sent to other authorities for comment and takes longer, and once it is published the new zone belongs to the erf.
Law stated as at 25 November 2026. This guide covers the City of Johannesburg’s land use scheme and Municipal Planning By-law. It is not advice on a particular property.
What is a consent use?
A consent use is a use that the scheme allows in a zone only with the City’s consent. In Johannesburg’s scheme these are each zone’s secondary land use rights, under that heading in the zone’s row of the scheme’s Table 2 (cl 10). The residential zones name them; in Business 1 and several other zones, they are every use the row neither permits outright nor prohibits. Clause 17 sends consent use applications to the City of Johannesburg Municipal Planning By-law, 2016, as amended in 2023, and section 19 of the By-law sets the procedure.1,2
The consent permits that use on that erf and changes nothing else: the zone and its limits stay. In the residential zones, the secondary rights include medical consulting rooms, a guest house, a salon, a place of instruction, religious purposes and a childcare centre. Hotels need consent in Residential 3 and 4; so do warehouses in Business 1 (the scheme’s Table 2).1
The City may refuse a consent, or grant it with any condition it sees fit. Among the conditions the By-law allows are these (s 19(7)):2
- that the consent lapses if the use has not begun, stops for a stated period, or reaches a stated date or event;
- that it may be withdrawn or amended if its conditions are broken or circumstances change;
- that the owner pays a contribution towards engineering services or, where the consent brings a higher residential density, gives land for open space or money instead.
A contribution not paid in time makes the consent lapse automatically (s 19(10) and (11)).2
What is a rezoning?
A rezoning amends the land use scheme for an erf. The By-law calls it the amendment of a provision of the land use scheme (s 4), and section 21 sets the procedure.2 Most rezonings move an erf into another use zone, such as from Residential 1 to Residential 3, so that it takes on that zone’s primary and secondary rights and its limits. A rezoning can also change the controls for the erf, so a plan needing far more height or floor area than its zone allows can call for one even when the use is permitted.
Notice of a rezoning reaches further than notice of a consent use. Once the City has issued the application’s registration reference number, notice is published in the Provincial Gazette and a newspaper. A site notice goes up the same day, letters go to the owners or occupiers of contiguous erven, including those across the street, and objectors have 28 days from publication (s 21(2)). The City also sends the application to the roads authority, neighbouring municipalities and others, who have 60 days to comment (s 21(4) and (5)).2
An approved rezoning takes effect only when the City gives notice of it in the Provincial Gazette, after the period for appeals. The application then becomes an amendment scheme, in operation from the date of publication (s 22(4) and (7)), and the new zone belongs to the erf, whoever owns it.2 The City may then levy contributions towards engineering services and, where density rises, open space (s 25(1)).2 Guide No. 1 follows a rezoning from first enquiry to promulgation.
Rezoning and consent use compared
| Item | Consent use | Rezoning |
|---|---|---|
| What it changes | Permits one use on the erf; the zone and its limits stay | The zone, or another provision of the scheme, for the erf |
| When it is the route | The use is a secondary right in the erf’s zone | The use is prohibited in the zone, or the erf needs limits its zone cannot give |
| The By-law | s 19 | ss 21 and 22 |
| Notice | A site notice, and letters to the owners or occupiers of contiguous erven, including those across the street | The Provincial Gazette and a newspaper, a site notice, and the same letters |
| Objections due | Within 28 days of the site notice’s first display | Within 28 days of publication |
| Comment from other authorities | None in s 19 | 60 days, for the roads authority, neighbouring municipalities and others |
| Decided by | An authorised official if unopposed; the Municipal Planning Tribunal if opposed | The same |
| Decision period in the By-law, if unopposed | 60 days from the end of the administrative phase | 90 days from the end of the administrative phase |
| After approval | The use must keep to the consent’s conditions | Notice in the Provincial Gazette makes it an amendment scheme, in operation from that date |
| Can it lapse? | Yes, where a condition provides for it, and if a contribution is not paid | Once in operation, it is part of the scheme |
| Contributions | Can be a condition of the consent | Can be levied after the amendment scheme comes into operation |
| Typical time in our practice, unopposed | 4 to 6 months | 6 to 9 months |
| Typical time with objections | 9 to 18 months | 9 to 18 months |
Source: the By-law, ss 16, 18, 19, 21, 22 and 25;2 the scheme, cl 10 and 17 and Table 2.1 The administrative phase runs from the date an application is complete and may last up to 12 months (s 57(3) and (6)); the decision periods start after it. Times are what our own matters typically take, not statutory periods or promises.
Do I need rezoning or a consent use?
Four checks, made in this order, usually settle it. Most plans need one application; some need two or three, prepared together.
- Read the erf’s zoning, with any annexure. A zoning certificate from the City names the use zone. Any annexure or schedule for the erf, even one carried over from a former town planning scheme, takes precedence over the scheme’s general clauses and can change what the zone allows (cl 3(3) and 6(2)(b)).1
- Find the use in your zone’s row of the scheme’s Table 2. Under “Primary land use rights”, the use needs no land use application. Under “Secondary land use rights”, it needs a consent use. Under “Prohibited land uses”, it is barred in that zone, and a rezoning is the usual route.1 Each row also settles a use it does not name: in the residential zones it is prohibited; in Business 1 and several other zones it needs consent. Go by the scheme’s definitions, not the everyday name: whether a plan is a guest house, a residential building or a home enterprise decides where it falls.
- Check the limits. Height, coverage, floor area ratio, density, building lines and parking each have their own rules, and some departures from them have narrower routes than a rezoning. The City’s written consent can allow up to 10% more coverage (cl 31(4)(b)) or 0.1 more floor area ratio (cl 33(1)(a)), as Departures and Permissions explains. An additional storey needs the City’s consent under clauses 28(3) and 40, a full consent rather than a written one. Building closer to the street than the building line in the scheme’s Table 7, or one an annexure sets, needs a building line relaxation (s 20 of the By-law).1,2 Where several limits must move a long way, a rezoning that sets new ones is usually the stronger application.
- Read the title deed. A condition registered against the title, such as one limiting the erf to one dwelling, or to residential use, can forbid what the zoning allows. An approval under the scheme does not lift it. Removing or amending it is an application of its own (Removal of Restrictive Conditions; ss 4 and 41 of the By-law), usually lodged with the consent use or rezoning.2
Read the erf’s zone, with any annexure
Find the use in your zone’s row of the scheme’s Table 2
- Primary land use rightNo land use application
- Secondary land use rightConsent use (By-law s 19)
- Prohibited land useRezoning (By-law s 21)
An unlisted use is prohibited in the residential zones but needs consent in Business 1 and several other zones.
Check the limits on size and position
- More coverage or floor area: written consent
- An extra storey: the City’s full consent
- Closer to the street: building line relaxation
- Several limits far beyond: a rezoning
Read the title deed
- A restrictive condition can bar the use
- Removing or amending it: By-law s 41
- Usually lodged with the main application
Then building plans, with a site development plan where clause 39 requires one
The four checks above in one picture. The scheme, any annexure and the title deed decide each case.
Building plans come after all of these, because a land use approval does not replace them. Outside Residential 1, building plans also wait for an approved site development plan, except on land with only a dwelling house (cl 39).1
| Plan | Zone | Usual route |
|---|---|---|
| A guest house in an existing house | Residential 1 | Consent use |
| Medical consulting rooms in a house | Residential 1 | Consent use |
| A childcare centre for 20 children | Residential 1 | Consent use; none is needed for six children or fewer (cl 22) |
| An office run from home by the person who lives there | Residential 1 | None, within clause 20’s conditions for a home enterprise |
| Offices as the main use | Residential 1 | Rezoning: offices are not among Residential 1’s rights |
| Townhouses in place of the house | Residential 1 | Rezoning, for example to Residential 2 or 3, where dwelling units are allowed |
| Two cottages beside the house | Residential 1 | None under clause 21, within its conditions; written consent if a unit has more than one storey |
| A hotel | Residential 3 | Consent use |
| A warehouse | Business 1 | Consent use |
| A house 1 m from the street on a 600 m² erf | Residential 1 | Building line relaxation: the street building line is 3 m |
Source: the scheme’s Tables 2 and 7, and cl 20, 21 and 22.1 Illustrative only: an annexure, a title condition or the erf’s own circumstances can change the answer.
When you need neither, or more than one
Neither, or something smaller. A primary right needs no land use application. Nor do some small uses: a home enterprise within clause 20’s conditions, a childcare centre for six children or fewer (cl 22), and up to two subsidiary dwelling units with a house on a Residential 1 erf (cl 21; see Guide No. 5).1 More houses on a Residential 1 erf can sometimes come from a subdivision instead of a rezoning, with one dwelling house on each new erf (cl 26(5)(a)).1
More than one. Some plans need two or three applications. A consent use for a guest house can need a building line relaxation for the rooms it adds. A rezoning can need a title condition removed, and erven in different use zones need a rezoning before they can be consolidated (cl 26(3)).1 We usually prepare and lodge them together, and the slowest sets the timetable.
Already operating. A use that started without the consent use or rezoning it needs is unlawful. The By-law says such a use must stop until the approvals are obtained, and that lodging an application does not allow it to continue (s 62(2)(b)(iii)).2 The route is the same application, often with a contravention notice to answer as well.
How long each takes, and what neighbours can do
In our practice, an unopposed consent use typically takes 4 to 6 months, and an unopposed rezoning 6 to 9 months. Either can take 9 to 18 months where objections have to be heard. They are drawn from our own matters, and are neither statutory periods nor promises. The By-law does not count the days between 15 December and 5 January (s 1), so an application advertised late in the year runs longer.2
Neighbours are told of both applications and may object. To count, an objection has to give the objector’s contact details and say which right, interest or legitimate expectation it protects; otherwise it may be disregarded (s 68).2 An objection does not decide the application; it changes who decides it. The applicant may answer within 14 days of receiving it, and the City then refers the application to the Municipal Planning Tribunal, which decides opposed applications (ss 16, 19(4) and 21(6)).2 A decision can be appealed within 28 days of the date the notice of it is dispatched (s 49(1)).2
Questions about rezoning vs consent use
Does a consent use change my zoning?
No. The zone stays as it is, with its limits, and the consent permits one use on the erf under the conditions the City sets. A rezoning changes the zone, and takes effect when it is published as an amendment scheme.
Can I apply for a consent use for any use?
Only for a use your zone’s row in the scheme’s Table 2 treats as a secondary right: in the residential zones, a use the row names; in Business 1 and several other zones, any use the row neither permits outright nor prohibits. A prohibited use usually needs a rezoning.
Is a consent use quicker and cheaper than a rezoning?
Usually. Its notice is local, section 19 sets no period for other authorities’ comment, and an unopposed one typically takes 4 to 6 months in our practice, against 6 to 9 for a rezoning. Its conditions can still carry costs, such as parking or a contribution towards engineering services.
Can I start the use while the application is being decided?
No. A use that needs a consent use or a rezoning is unlawful until it is approved. The By-law says it must stop until then, and that lodging an application does not allow it to continue (s 62(2)(b)(iii)).
What if my title deed forbids the use?
Then an approval under the scheme cannot permit it on its own. The condition has to be removed or amended under the By-law (ss 4 and 41), usually in an application lodged with the consent use or rezoning. Where a title condition allows a use only with the City’s consent, that consent is applied for under the same provisions (s 4).
Not sure which application your plan needs?
Tell us the erf and what you want to build or run there. A planner will check its zoning, any annexure and the title deed, name the applications the plan needs and say how long they usually take.
Speak to a PlannerFind your route in three questions
- Telephone
- +27 10 442 5522
- +27 79 375 2704
Related services: Consent Use · Rezoning · Departures and Permissions · Building Line Relaxation · Removal of Restrictive Conditions
Read next
Sources
- ↑ City of Johannesburg Land Use Scheme, 2018, as amended 2025 (Provincial Notice 390 of 2026, Gauteng Provincial Gazette 193, 24 June 2026), the City’s copy, from which the clause and table numbers are taken: City of Johannesburg.
- ↑ City of Johannesburg Municipal Planning By-law, 2016, as amended in 2023 (Local Authority Notice 447 of 2024, Gauteng Provincial Gazette 117, 3 April 2024): the amended text on Open By-laws, and the City’s copy.
About the author
Glensburg Town Planners
Glensburg Town Planners is a planning, architecture and development practice based in Illovo, Johannesburg. Its publications are written and checked by the planners and architects who prepare the applications they describe.
Cite this guide
Glensburg Town Planners (2026) Rezoning or Consent Use? Which Application Your Plan Needs. Glensburg Guide No. 7. Available at: https://glensburg.co.za/insights/guides/rezoning-vs-consent-use/
How this guide is maintained
- Version 1 . First published. Checked against the City’s copy of the land use scheme and the amended text of the By-law on 25 November 2026. We review it when either is amended and record each change here.
This guide explains the law in general terms, as at the date above. It is not advice on any particular property.